WEEK 10. 11-09-12.
PROGRESS:
some more progress with reinforcement for concrete floor.
its slow work to make up these reinforcement cages.
2/3guys on site today so my chat with Martin has worked o.k.
I met him today aswell and he seems more focused on the job.
Tomorrow wil be a big day with excavation works (digging
out of ground) to allow placement of retaining walll that will
hold back height difference between rear block and existing.
Also some special help drafted in today to speed things up: