PROGRESS:

site works well underway:
 

 
 
stone wall nearly complete.

Gateway and cattle grid to be discussed.
 
Area to rear leveled out - trees removed to facilitate view.
 
path to front house in place
 
 boundary wall at retaining wall in progress.
 
Inside:
 
panelling (wainscotting) to both front rooms complete. 

Concrete floor to kitchen laid.
 
stairs delivered but brought back to carpenter for minor adjustment.
 
kitchen delivered as you know.
 
 
 

 