PROGRESS

bit more plasterboard to walls - a lot more done to ceilings. 

wall built to boiler room area.

 I told you about Martins new schedule and his promise to finish 03 June.

(this is the Bank Holiday weekend) 

I will scan this in and include in next post. 

I have given Martin an updated version of the Landscape plan - he will start some landscaping this week. 

This means that the two trees at front will come down  - I cant see any other way. 

I have asked him to replant the 2 cherry trees as mentioned by Paula a.s.a.p.

I have asked him to get semi mature trees to give a head start.   

Also the set back to the front will be provided - Mayo Co Co Roads are in discussion with 

neighbor regarding his set back. I would hope that Mayo Co Co wil do some remedial works

to existing road outside house - however this will not happen quickly as - to date - contact 

with Mayo Co Co roads has been problematic (1 month to return a phone call).

 2 questions:

I have a question regarding stairs between hallway and living areas - (see photo below.)

Also, should we apply to remove ESB pole (see photo below). It is directly in line with view Croagh Patrick - these moves normally take a long time so best to enquire now

Also it may be costly so may not be a priority.


most rooms now have plasterboard walls and ceilings

 




new wall to boiler room

?????I was thinking that the finished stairs should move towards centre rather than pushed to the right as shown??????


should we apply to remove ESB pole?????

 