Tuesday, 12 March 2013

WEEK 33  - 07 - 03-13. 

PROGRESS:

lot of work done inside over last few days. 

1. existing walls to cottage sheeted with plastic membrane and given timber frame to allow air gap and fixing for drylining.

2. Timber OSB board finish to inside leaf of timber frame extension with insulatyion wool between.

3. Rooflight to area over stairs to hallway 

4. Timber ccollar (horizontal timbers) to roof in timber frame extension.