Wednesday, 27 March 2013

Monday, 25 March 2013

WEEK 35  - 25 - 03-13. 

PROGRESS:

finally some plasterboard in place and beginning to look like a house. 

most of existing house complete with plasterboard finish,

first fix electrics complete. 

first fix plumbing complete.









Saturday, 16 March 2013

WEEK 34  - 15 - 03-13. 

PROGRESS:

 

first fix electrics complete. 

 

 




windowboards complete



WEEK 34  - 13 - 03-13. 

PROGRESS:

roof to rear nearly apart from area to chimney.


 these photos show bathroom area which has pipes in place for w.c./ bath and w.h.b.

shower

bath area - freestanding - taps to middle

area for counter (under window) and w.h.b.

whole bathroom area behind partition
 

Tuesday, 12 March 2013


WEEK 34  - 11 - 03-13. 

PROGRESS:

roof to rear nearly finished.
 
roofligts in place and look good.
 
both electrically operated.
 
existing cottage ready for final internal finish - 60mm drylining (insulation plus plasterboard)
 
   






WEEK 33  - 07 - 03-13. 

PROGRESS:

lot of work done inside over last few days. 

1. existing walls to cottage sheeted with plastic membrane and given timber frame to allow air gap and fixing for drylining.

2. Timber OSB board finish to inside leaf of timber frame extension with insulatyion wool between.

3. Rooflight to area over stairs to hallway 

4. Timber ccollar (horizontal timbers) to roof in timber frame extension.


















WEEK 33  - 03 - 03-13. 

PROGRESS:

flat roof over link done,













WEEK 32  - 29 - 02-13. 


 

 PROGRESS:

flat roof over master bedroom done,