WEEK 29 - 31 - 01-13.
PROGRESS:
slates to dormers complete.
all leadwork to roof finished.
rest of roof postponed due to bad weather.
carpentry to first floor finished.
PVC windows to rear due for delivery today 31st.
note: ESB pylon is in fairly visible - in the way???
if we ever need to move it for visual reasons then it would be good to inform ESB now - they need a good 2 months to do this - it also comes at a cost.
slate to dormers complete |
hallway - with future doorway right and left |
hallway |
bathroom area - overall dimensions approx 2 meter x 3 meter. |