WEEK 20. 12-12-12.
PROGRESS:
felt and battens to main roof of extension
(green water proof material with timber battens nailed on top to attach slates)
side portion to gable of extension made in timber.
some work to walls inside.
windows as you know ordered.
delivery dates:
sliding sash and front doors (anything timber) - 14 Jan 2013
all other (pvc) - 21-24 Jan 2013
slates ordered as per sample shown in thicker variety (better weatherproof and variety in grain/ texture)
I have made the April 27th deadline clear to Martin.
rear of site |