WEEK 15. 12-10-12.
PROGRESS:
only got to site at end of day.
link between old and new foundations poured and ready.
we have opted for a block wall betwen oil boiler annd hallway - as opposed
to timber stud that was on drawings - blockwork safer.
they have also started on the repair of existing wall and will be putting blocks up there
Id imagine tomorrow.
the man in white jacket has worked for 40 years on building sites and is finishing today - I brought him a bottle of whiskey!! |
retaining wall finished and back filled |
ESB box |
work to top of wall |
raft foundation to rear extension - just a mass slab of concrete really. |