PROGRESS:

discussion taken place with Emmett (adjoining landowner) and permission
given to demolish wall and replace with new - to be stone wall at level of laneway.
solution discussed with engineer for cost effective retaining wall.
 

boundary marked out for future reference
boundary area cleared

 area to ground for new extension made level, filled and ready to be built on.

area of future living/ dining/ kitchen made ready



TO DISCUSS
Martin will send a quotation for the intended work to boundary retaining wall that we 
hadn't anticipated - about 15 meters long at approx. (my guess) 135 euro per meter  - 2000 euro. 
i think the cost of the actual stone wall on top should remain with Martain as this would heve been in drawings. I will chat to him today about that.
 
Blocklayers back on site today.