Friday, 13 September 2013

sorry about delay in posting.

see below progress...........

painting to downstairs complete.

floor to  living and snug complete

kitchen units constructed and in place

some skirting and architrave work done.

stairs to be delivered monday. 



pre painting showing floor

painting complete


floor tiles yet to come - dishwasher and fridge yet to be installed.


utility - washing machine and freezer yet to be installed

utility


Sunday, 1 September 2013

 lot of work done to outside:

stone facing to wall near front door.
cow grate dug out and stone wall left and right.
stone wall as a whole nearly finished
concrete steps in place.
doorway in stonewall to left of house in place.
grass seed to lawn growing.
trees cuts away to show view of Reek.


.