Sunday, 21 July 2013

see photo of timber floor.
and finished screed floor to kitchen/ dining/ living and snug
also master bedroom.

and finally, the front wall is looking really good.











Thursday, 18 July 2013

We have had a chat here and Martin has agreed to have thge front of house ready by Thursday.

He will put in some furniture (bed, table, sofa) tha will do temporally.

I will call about all this.

see photos











Tuesday, 16 July 2013

painting well under way.

electrics finished.

concrete floors must dry out before timber floors can be laid.

some wainscoting/ timber detail in place.

timber floors upstairs being laid.

 













Tuesday, 9 July 2013

Tuesday 09-07-2013

electrician nearly finished on site
 
lot of painting done inside - white coat to begin.
colors come later.

Ive talked to Martin about date in July.
House will be habitable but not finished - you will be able to
have an input first hand into last few details which is handy.



 




 visitors to site today - I think they liked it!!!





Monday, 1 July 2013

.

Friday, 28 June 2013



WEEK 44.

 timber floors delivered.

solar panel in place.

screed floors laid on Friday and are drying out.

pipes are ready for radiators and sanitary downstairs.

most ceiling areas are ready for final coat plaster.