Tuesday, 18 June 2013

WEEK 43  - 17 - 10 -13.  

sorry - these are actually from last Friday.

so there will have been more progress since then.

 
space above kitchen - I have asked to close out - with 2 doors centrally located - to access storage later


looking good!!!

utility area is rendered - all new area now rendered.
 this is the fireplace to date.

decision to be made  - to infill areas left and right with bookcase/ storage????

or leave the firreplace and chimney freestanding???

it will have a plaster render finish.










Tuesday, 11 June 2013

WEEK 42  - 08 - 10 -13.  

render finished outside -

only timber cladding to go at utility and snug

plenty of wet plaster work and drylining going on inside - again these are the final few bits being finished.







render to outside

side walls that make up fireplace.

area that contains store above kitchen



Monday, 3 June 2013

WEEK 41  - 23 - 05 -13.  

render finished inside (render to downstairs master bedroom, hall, front rooms etc)
 
portion of existing stone wall left exposed downstairs






Render to front has a undercoat in place and all new build walls have render complete - 
plaster to outside should be finished Wednesday. 







stone wall to front nearly done - stone wall to side nearing completion.







Did ye get a chance to look at layout for parking and gates etc...
also any opinions on stone plaques???