Monday, 11 February 2013

WEEK 30  - 07 - 02-13. 
 
 PROGRESS:
 
bit more of roof done.
 
roof to new portion to rear nearly complete.
 
few decisions to make this week:
 
color of fascias/ soffits to existing cottage (not front facade)
 
I know the front has decorative edges..........we can decide paint color later.....
..........and the rear new portion will be the light oak imitation p.v.c.

but the portion in between - the stem of the T shape of the existing cottage???

This - in my mind - will need to match the color of the existing...when we choose a color........should they just make a timber edge to begin and will be painted later.

Also the edges to the flat roof areas......will be best to be in p.v.c. for durability
...............but wont look good in light oak - how about a plain black or grey???



 
 




Thursday, 7 February 2013

WEEK 30  - 07 - 02-13.

PROGRESS:
roof to rear.

potential carved stone  above doorway??????

dampproofing (injected every 120mm)





Tuesday, 5 February 2013


WEEK 30  - 05 - 02-13.

PROGRESS:



 
slates to front of roof complete.
 
more to rear.

Sunday, 3 February 2013


WEEK 29  - 02 - 02-13.

PROGRESS:
slates to front of roof complete.
and partly to rear
roofers were there Saturday to catch up.


















some more studwork walls to master bedroom (ensuite area and walk in wardrobe)
are complete