WEEK 18. 29-11-12.
PROGRESS:
bit dark when I got there - but good progress made.
block wall to timber frame portion complete.
(the 2 end portions - snug and utility - will remain timber clad which is done at a later date)
Windows supplier will be there tomorrow. (Munster Joinery - have worked with before and they will do the job ok)
He will measure openings and on the basis of this and
my drawings will begin manufacture and have the windows delivered before X mas.
Will only take 1 day to fit windows when they arrive.